Water Treatment
Holdenhurst WRC
A £30 million investment by Wessex Water to protect Bournemouth's popular beaches.

Delivering critical infrastructure projects across the water, environmental and civil engineering sectors throughout the United Kingdom.
Water Treatment
A £30 million investment by Wessex Water to protect Bournemouth's popular beaches.
ESG
Its amazing to see how our time can benefit the sanctuary and its residents.
ESG
From our community to yours.
Trenchless Technology
Bristol Water water mains renovation project delivering a 10.5km package from Ditcheat to Wraxall, Shepton Mallet.
Bathing Water Improvements
Beaumont Infrastructure operate at the Strategic Partner level within the Wessex Water AMP 6 Delivery programme.
Potable Water Mains
Providing a secondary supply route between Wells and Glastonbury for maintaining a safe supply of water.
Tunnelling
Wastewater
Water
Electrical Infrastructure
The world's largest offshore wind farm. Construction of the onshore 320kV HVDC cable route for phases A and B, installing 182 cable drums containing 120km of HVDC cable and 24km of 400kV cable.
Electrical Infrastructure
The UK's highest altitude wind farm with 76 Siemens 3.0MW turbines. Design and installation of 312km of 33kV cabling, 27 substations, fibre optic network, 900 cable terminations, earthing systems and SCADA controls.
Electrical Infrastructure
The largest consented tidal energy project globally. Electrical infrastructure including 33kV circuit breaker, 7km of 132kV cable, landfall substation design and construction, SCADA system and protection schemes.
Electrical Infrastructure
EDF Renewables' largest onshore wind farm with 59 Vestas V90 3.0MW turbines. Full EBoP contractor delivering 40km of cable trenches, 240km of 33kV cabling, substation compound with 2 x 120MVA 33/132kV transformers.
Electrical Infrastructure
60-turbine wind farm in the Lammermuir Hills. Delivery of 110km of 33kV cabling, 40km of fibre optic cable, 60 turbine substations with switchgear and 2.8MVA transformers, SCADA and harmonic filters.
Electrical Infrastructure
27-turbine wind farm in North Wales. Installation of two 70MVA 132kV/33kV grid transformers, 132kV busbar network, duplicate 33kV switchboards and 181.5km of onsite 33kV cabling.
Electrical Infrastructure
24-turbine wind farm generating 250GWh annually. EBoP contractor designing and constructing the 132kV substation, grid transformers, circuit breakers, switchgear and 22.3km of 33kV onsite cabling.
Electrical Infrastructure
19 Siemens 3.2MW Direct Drive turbines. Installation of 90MVA 132/33kV grid transformer, 6-panel 33kV indoor switchboard, 55km of 33kV cabling and one of the first point-on-wave circuit breaker controllers in the UK.
Electrical Infrastructure
Subsidy-free wind farm with 20 Nordex N90 2.5MW turbines. Full EBoP delivery including 132/33kV transformer, 40km of 33kV HV cable, Schneider 33kV switchboard, SCADA integration and fibre optic monitoring.
Electrical Infrastructure
One of the UK's first subsidy-free wind farms with 13 Vestas V136-3.6MW turbines. Complete electrical infrastructure including 132kV and 33kV equipment, 50/60MVA grid transformer and 90km of 33kV cabling.